Information & Publications
Document Timeline
Last updated September 2026
Documents will continue to be added to this timeline.
-
MilestoneArea Structure Plan Boundary Identified
Area Structure Plan Boundary Identified
2013
2013 -
2019
-
MilestoneTri-Municipal Area Structure Plan
Tri-Municipal Industrial Partnership Area Structure Plan (Bylaw 19-815)
September 2019
Bylaw 19-815, passed by the MD of Greenview on September 9, 2019, adopting the Tri-Municipal Industrial Partnership Area Structure Plan. The plan covers approximately 75 square kilometres of Crown land about 40 kilometres south of Grande Prairie, and sets out where heavy industrial development, natural features, utilities and transportation corridors belong.
Sep2019 -
2020
-
Environmental and WaterEco-Industrial District MOU
MOU for Eco-Industrial District
February 2020
MD of Greenview / City of Grande Prairie / County of Grande Prairie
The GIG was originally conceived by the Tri-Municipal Industrial Partnership (TMIP) between the MD of Greenview and its closest neighbours, the City of Grande Prairie and the County of Grande Prairie. Their common goal was to develop an Eco-Industrial District to “coordinate the orderly development of industrial services… in a manner that supports provincial and municipal economic, social and environmental priorities.” The GIG is the result of this collaboration.
Feb2020 -
2021
-
Strategic PlanGIG Strategic Business Plan
Greenview Industrial Gateway Strategic Business Plan
2021
Strategic business plan for the Greenview Industrial Gateway, covering legal and legislative requirements, infrastructure, stakeholder partnerships, governance and promotion.
2021 -
Environmental and WaterWater Availability Assessment
Water Availability Assessment for the Greenview Industrial Gateway (V2)
June 2021
WaterSMART Solutions Ltd.
Assessment of water availability for new allocations from the Smoky River, including existing licence holders and storage needs, based on a hypothetical petrochemical development requiring up to 50 million m³/year. Subsequent GIG planning considered approximately 24 million m³/year.
Wonder Valley Context
Wonder Valley intends to remain below a 6 million m³/year allocation, therefore historic figures should not be interpreted as its current requirements. Wonder Valley’s process-water strategy uses a recirculating loop with makeup water, potentially reducing source-water withdrawal to approximately 1.4 million m³/year. Combined-cycle generation provides a conservative water-use basis; other options may require substantially less water.
Jun2021 -
Environmental and WaterPublic Lands Reservation Map (PNT 190055)
Public Lands Act Reservation PNT 190055 Map Package
August 2021
Alberta Environment and Parks
Map package for Public Lands Act reservation PNT 190055, showing the GIG Area Structure Plan (ASP) boundary.
Aug2021 -
Committee MeetingGIG Committee Meeting
Greenview Industrial Gateway Committee Meeting Agenda Package
November 2021
Agenda package for the November 8, 2021 meeting of the Greenview Industrial Gateway Committee, including the October 13, 2021 minutes.
Nov2021 -
2022
-
Environmental and WaterIntake Environmental Overview
Appendix I: Greenview Industrial Gateway Intake Environmental Overview
September 2022
Associated Engineering
Environmental overview for the proposed GIG water intake. The overview considered various potential industrial uses for the GIG (e.g. petrochemical development). The report is included as historic context for the MD of Greenview’s 2025 Water Act application (Appendix I).
Wonder Valley Context
This report was completed prior to identification of the Wonder Valley Data Centre project as a possible occupant of the GIG.
Sep2022 -
2023
-
Environmental and WaterGeotechnical2 documentsView documentsHover or select to expand
March 2023
Environmental and WaterGeotechnicalRaw Water Intake Preliminary Design
Appendix III: Raw Water Intake Preliminary Design Final Report
March 2023
Northwest Hydraulic Consultants
Preliminary design report for the GIG raw water intake. The preliminary design considered various potential industrial uses for the GIG (e.g. petrochemical development). The report is included as historic context for the MD of Greenview’s 2025 Water Act application (Appendix III).
Wonder Valley Context
The report was completed prior to identification of the Wonder Valley Data Centre project as a possible occupant of the GIG.
GeotechnicalIntake Preliminary Selection Overview
Appendix IV: Intake Preliminary Selection Overview
March 2023
Overview of the preliminary selection of the GIG water intake. The overview considered various potential industrial uses for the GIG (e.g. petrochemical development). The report is included as historic context for the MD of Greenview’s 2025 Water Act application (Appendix IV).
Wonder Valley Context
The overview was completed prior to identification of the Wonder Valley Data Centre project as a possible occupant for the GIG.
Mar2023 -
GeotechnicalGeotechnical Investigation
Appendix V: Geotechnical Investigation, Greenview Industrial Gateway
June 2023
Englobe
Geotechnical investigation for the GIG. The investigation considered various potential industrial uses for the GIG (e.g. petrochemical development). This document is included as historic context for the MD of Greenview’s 2025 Water Act application (Appendix V).
Wonder Valley Context
The geotechnical investigation concluded prior to identification of the Wonder Valley Data Centre project as a possible occupant for the GIG.
Jun2023 -
Environmental and WaterGeotechnical2 documentsView documentsHover or select to expand
August 2023
Environmental and WaterGeotechnicalRaw Water Pipeline Alignment Options
Appendix VIII: Raw Water Pipeline Alignment Options
August 2023
Associated Engineering
Alignment options for the GIG raw water pipeline. The options considered various potential industrial uses for the GIG (e.g. petrochemical development). This document is included as historic context for the MD of Greenview’s 2025 Water Act application (Appendix VIII).
Wonder Valley Context
The alignment options review was completed prior to identification of the Wonder Valley Data Centre project as a possible occupant for the GIG.
GeotechnicalRaw Water Storage Ponds Concept
Appendix IX: Raw Water Storage Ponds Concept
August 2023
Associated Engineering
Concept for the GIG raw water storage ponds. The concept considered various potential industrial uses for the GIG (e.g. petrochemical development). This document is included as historic context for the MD of Greenview’s 2025 Water Act application (Appendix IX).
Wonder Valley Context
The concept was completed prior to identification of the Wonder Valley Data Centre project as a possible occupant for the GIG.
Aug2023 -
GeotechnicalHistorical Resources Impact Assessment
Appendix VI: Historical Resources Impact Assessment
September 2023
Circle CRM Group
Historical Resources Impact Assessment for the GIG. The assessment considered various potential industrial uses for the GIG (e.g. petrochemical development). This document is included as historic context for the MD of Greenview’s 2025 Water Act application (Appendix VI).
Wonder Valley Context
The assessment concluded prior to identification of the Wonder Valley Data Centre project as a possible occupant of the GIG.
Sep2023 -
2024
-
Environmental and WaterPre-Disturbance Wildlife Sweep
GIG Pre-Disturbance Wildlife Sweep Report
May 2024
Wildlife sweep of the GIG site completed before ground disturbance.
Wonder Valley Context
The sweep was completed prior to identification of the Wonder Valley Data Centre project as a possible occupant for the GIG.
May2024 -
Environmental and WaterEnvironmental Overview
Appendix II: Environmental Overview
July 2024
Associated Environmental Consultants
Environmental overview for the GIG. The overview considered various potential industrial uses for the GIG (e.g. petrochemical development). This document is included as historic context for the MD of Greenview’s 2025 Water Act application (Appendix II).
Wonder Valley Context
This report was completed prior to identification of the Wonder Valley Data Centre project as a possible occupant of the GIG.
Jul2024 -
Indigenous ConsultationPublic Lands Act Consultation Confirmation
Public Lands Act Indigenous Consultation Confirmation
August 2024
Alberta Forestry and Parks
Letter from Alberta Forestry & Parks confirming the Indigenous consultation adequacy decisions made on August 20, 2021 for taking up the GIG lands for future sale or development.
Wonder Valley Context
This consultation considered various potential industrial uses for the GIG, primarily petrochemical development, and concluded prior to identification of the Wonder Valley Data Centre project as a possible occupant for the GIG.
Aug2024 -
Environmental and Water3 documentsView documentsHover or select to expand
November 2024
Environmental and WaterPre-Consultation Assessment (3.5 million m³)
Pre-Consultation Assessment FNC202455127: Provisional Water Intake
November 2024
Aboriginal Consultation Office
Pre-consultation assessment by Alberta’s Aboriginal Consultation Office for a proposed diversion of up to 3.5 million m³/year from the Smoky River for the GIG water intake, well within previous GIG planning for approximately 24 million m³/year. The assessment includes the Office’s consultation recommendation.
Wonder Valley Context
The Wonder Valley project intends to remain below a 6 million m³/year allocation. Wonder Valley’s process-water strategy uses a recirculating loop with makeup water, potentially reducing source-water withdrawal to approximately 1.4 million m³/year. Combined-cycle generation provides a conservative water-use basis; other options may require substantially less water.
Environmental and WaterPre-Consultation Assessment Request (6 million m³)
Pre-Consultation Assessment Request FNC202455665: Provisional Water Intake
November 2024
Pre-consultation assessment request for a proposed diversion of up to 6 million m³/year from the Smoky River for the GIG water intake, well within previous GIG planning for approximately 24 million m³/year.
Wonder Valley Context
Wonder Valley’s process-water strategy uses a recirculating loop with makeup water, potentially reducing source-water withdrawal to approximately 1.4 million m³/year. Combined-cycle generation provides a conservative water-use basis; other options may require substantially less water.
Environmental and WaterPre-Consultation Assessment (6 million m³)
Pre-Consultation Assessment FNC202455665: Provisional Water Intake
November 2024
Aboriginal Consultation Office
Pre-consultation assessment by Alberta’s Aboriginal Consultation Office for a proposed diversion of up to 6 million m³/year from the Smoky River for the GIG water intake, well within previous GIG planning for approximately 24 million m³/year. Includes the Office’s consultation recommendation.
Wonder Valley Context
Wonder Valley’s process-water strategy uses a recirculating loop with makeup water, potentially reducing source-water withdrawal to approximately 1.4 million m³/year. Combined-cycle generation provides a conservative water-use basis; other options may require substantially less water.
Nov2024 -
Environmental and WaterWater Intake and Transfer Station Design
Appendix VII: Preliminary Design Report, Water Intake and Raw Water Transfer Station
December 2024
MPE, a Division of Englobe
Preliminary design report for the GIG water intake and raw water transfer station. Appendix VII to the Water Act application.
Wonder Valley Context
Wonder Valley’s process-water strategy uses a recirculating loop with makeup water, potentially reducing source-water withdrawal to approximately 1.4 million m³/year. Combined-cycle generation provides a conservative water-use basis; other options may require substantially less water.
Dec2024 -
2025
-
Environmental and WaterLand Requirements for Storage Ponds
Appendix X: Estimated Land Requirements for Raw Water Storage Ponds
February 2025
Associated Engineering
Estimated land requirements for the GIG raw water storage ponds. Appendix X to the Water Act application.
Feb2025 -
Environmental and WaterWater Act Application
Alberta Water Act Application for Approval
March 2025
The MD of Greenview’s application for approval to develop the GIG in compliance with Alberta’s Water Act.
Wonder Valley Context
If a licence is granted under the Act, the MD intends to transfer the licence to the Wonder Valley project.
Mar2025 -
2026
-
Letter of Support3 letters of supportView documentsDesignated Industrial Zone application
March 2026: Letters of support for the Designated Industrial Zone application
Letter of SupportLetter of Support: MD of Greenview
Letter of Support for the Designated Industrial Zone Application: MD of Greenview
March 2026
Letter from the MD of Greenview to Alberta’s Minister of Environment and Protected Areas supporting the application to designate the Greenview Industrial Gateway as a Designated Industrial Zone.
Letter of SupportLetter of Support: County of Grande Prairie
Letter of Support for the Designated Industrial Zone Application: County of Grande Prairie No. 1
March 2026
County of Grande Prairie No. 1
Letter from the County of Grande Prairie No. 1 to the Government of Alberta supporting the MD of Greenview’s application to designate the Greenview Industrial Gateway as a Designated Industrial Zone.
Letter of SupportLetter of Support: City of Grande Prairie
Letter of Support for the Designated Industrial Zone Application: City of Grande Prairie
March 2026
City of Grande Prairie
Letter from the City of Grande Prairie to Alberta’s Minister of Environment and Protected Areas supporting the MD of Greenview’s application to designate the Greenview Industrial Gateway as a Designated Industrial Zone.
Mar2026 -
MilestoneDesignated Industrial Zone Granted
Designated Industrial Zone Granted
August 2026
The Government of Alberta granted Designated Industrial Zone status to the Greenview Industrial Gateway. It is the second Designated Industrial Zone in Alberta.
Aug2026
All Documents (25)The same documents shown on the timeline above, listed in one place. The category filter applies here too.
- Letter of SupportPDFMarch 2026Letter of Support for the Designated Industrial Zone Application: MD of GreenviewMD of GreenviewPDF
- Letter of SupportPDFMarch 2026Letter of Support for the Designated Industrial Zone Application: County of Grande Prairie No. 1County of Grande Prairie No. 1PDF
- Letter of SupportPDFMarch 2026Letter of Support for the Designated Industrial Zone Application: City of Grande PrairieCity of Grande PrairiePDF
- Environmental and WaterPDFMarch 2025Alberta Water Act Application for ApprovalMD of GreenviewPDF
- Environmental and WaterPDFFebruary 2025Appendix X: Estimated Land Requirements for Raw Water Storage PondsAssociated EngineeringPDF
- Environmental and WaterPDFDecember 2024Appendix VII: Preliminary Design Report, Water Intake and Raw Water Transfer StationMPE, a Division of EnglobePDF
- Environmental and WaterPDFNovember 2024Pre-Consultation Assessment FNC202455127: Provisional Water IntakeAboriginal Consultation OfficePDF
- Environmental and WaterPDFNovember 2024Pre-Consultation Assessment Request FNC202455665: Provisional Water IntakePDF
- Environmental and WaterPDFNovember 2024Pre-Consultation Assessment FNC202455665: Provisional Water IntakeAboriginal Consultation OfficePDF
- Indigenous ConsultationPDFAugust 2024Public Lands Act Indigenous Consultation ConfirmationAlberta Forestry and ParksPDF
- Environmental and WaterPDFJuly 2024Appendix II: Environmental OverviewAssociated Environmental ConsultantsPDF
- Environmental and WaterPDFMay 2024GIG Pre-Disturbance Wildlife Sweep ReportPDF
- GeotechnicalPDFSeptember 2023Appendix VI: Historical Resources Impact AssessmentCircle CRM GroupPDF
- Environmental and WaterGeotechnicalPDFAugust 2023Appendix VIII: Raw Water Pipeline Alignment OptionsAssociated EngineeringPDF
- GeotechnicalPDFAugust 2023Appendix IX: Raw Water Storage Ponds ConceptAssociated EngineeringPDF
- GeotechnicalPDFJune 2023Appendix V: Geotechnical Investigation, Greenview Industrial GatewayEnglobePDF
- Environmental and WaterGeotechnicalPDFMarch 2023Appendix III: Raw Water Intake Preliminary Design Final ReportNorthwest Hydraulic ConsultantsPDF
- GeotechnicalPDFMarch 2023Appendix IV: Intake Preliminary Selection OverviewPDF
- Environmental and WaterPDFSeptember 2022Appendix I: Greenview Industrial Gateway Intake Environmental OverviewAssociated EngineeringPDF
- Committee MeetingPDFNovember 2021Greenview Industrial Gateway Committee Meeting Agenda PackageMD of GreenviewPDF
- Environmental and WaterPDFAugust 2021Public Lands Act Reservation PNT 190055 Map PackageAlberta Environment and ParksPDF
- Environmental and WaterPDFJune 2021Water Availability Assessment for the Greenview Industrial Gateway (V2)WaterSMART Solutions Ltd.PDF
- Strategic PlanPDF2021Greenview Industrial Gateway Strategic Business PlanMD of GreenviewPDF
- Environmental and WaterPDFFebruary 2020MOU for Eco-Industrial DistrictMD of Greenview / City of Grande Prairie / County of Grande PrairiePDF
- MilestonePDFSeptember 2019Tri-Municipal Industrial Partnership Area Structure Plan (Bylaw 19-815)MD of GreenviewPDF